At the beginning of the summer Mor-Gran-Sou Electric Coopertaive began to reconstruct the transmission line from the Cannon Substation to the Grant Substation near Carson.
The operations department along with engineers from Innovative Energy Alliance Cooperative, a cooperative owned by four North Dakota distribution cooperatives included Mor-Gran-Sou Electric, diligently planned for the execution of this project that is soon to be complete.
This project allowed Mor-Gran-Sou Electric to retire 33-miles of overhead transmission line and poles and replace it with 14-miles of 69kV of new overhead transmission line and infrastructure.
The cooperative worked with area landowners to obtain easements for the new route which allowed Mor-Gran-Sou Electric to cut the transmission line route in half.